Spring Maintenance 2018


MAINTENANCE IS COMPLETED AS OF APRIL, 2018.

Timeline of the 2018 Berm Maintenance Project:
Starting March 3rd, the main line will be closed to allow for several major range improvements. Work involved in this phase of improvements will include range regrading to facilitate better water drainage and extending/rebuilding berms to aid future maintenance and increase safety. We plan to keep this page regularly updated with photos and descriptions of the progress being made from start to finish.

The expected time of completion is approximately four weeks.


March 4th, 2018

Feats of superhuman strength or determination of a heckuva hard working crew? The target bases have all been dug out and relocated to the bench area.

Moving them was the first step in the process of regrading the range to improve drainage. It also makes it a lot easier to get equipment and machinery in and out for rebuilding the pistol berm.


March 5th, 2018

“Moving dirt” and “gripping action shots” are a hard combination to pull off without either an avalanche or some wrestling going on, so we grabbed a few quick shots of the kind of heavy equipment needed to make all this happen in a reasonable amount of time.


March 9th, 2018

The weather has been in our favor the past few days, and progress has been great. Sunny days means dry ground. Dry ground means 20-ton trucks can load up and travel faster. Also, a lot of the work is killing two birds with one stone, as we are carving out new bays from mountains of dirt and using what’s extracted to build and reinforce nearby berms.


March 12th, 2018

If you like excavation and heavy machinery, you’ve got a couple more days of fun photos. If you’re more into the details, we’ve got good news for you – look forward to our update at the end of the week. 😉


March 20th, 2018

It seems I get a demerit here for this one. I jumped the gun on new info and the reality is we still have plenty more to move and do before committing to any particular projects. So, for that I apologize and I hope you will accept my gift of a large vehicles and dirt.


March 22nd, 2018

CALLING ALL VOLUNTEERS!

Come team up with staff and fellow members in some much needed maintenance and construction at MGAC. Spend a few days, or even just a few hours… any and all help is greatly appreciated!

DATES:

  • Fri & Sat, March 23rd & 24th – 9AM to 1PM
  • Mon – Sat, March 26th – March 31st – 9AM to 1PM

EQUIPMENT TO BRING (optional, but helps):

  • Fan rakes
  • Generators
  • Fans
  • Tools: Hammers, saws, drills, and shovels

ON THE TO-DO LIST:

  • Clean up bays in the back of spent brass, hulls and wadding.
  • Building heavy duty shelving units for tractor equipment.
  • Construction of a wooden fence
  • Pipe laying

Come out and support your club; we could use your help!

Thank you,
Billy “Tank” Tutko


April 2nd, 2018

THE HOME STRETCH IS HERE. VOLUNTEER!

Get a sneak peek at what has been done by coming out and giving us a hand.

Volunteers needed Tuesday, April 3rd and Wednesday, April 4th to help get the range ready for Thursday, April 5th opening.

We need strong able bodies to help set the railroad ties back into place on all four berms and to complete a few last minute touch ups.

Your time and help is greatly appreciated!

Thanks,
Angie Weldon, Manager


April 3rd, 2018

THE POWER OF TEAMWORK – RE-OPENING APRIL 5TH, 2018

Great news!

We are ready for opening on Thursday, April 5th !

We had such a great turn out of volunteers today that they will have everything done by end of day today!
So, looks like tomorrow the staff will take a much needed day off and will see everyone on the range on Thursday, April 5th!

Again, thank you to all our volunteers that came out and pitched in to support their club!

See you on the range,
Angie Weldon, Manager


April 5th, 2018

MAIN LINE NOW OPEN, UPDATE ON REMAINING WORK

The bulk of the work has been completed and the main line is now open again. Welcome back!

MEANWHILE…

We are currently preparing to de-lead the bays in the back, starting with the cowboy bays and working our way to the 600-yard bench rest. This should take 5-7 days to complete and we begin work tomorrow. The 600-yard range is tentatively open. Shooters should call first before coming out to be sure that it is available. We’d hate to see someone make the trip and it isn’t open for them. Please, please call first. (941) 322-0055

June 15th, 2018

MAIN LINE OPEN, all construction complete.

The bulk of the work has been completed and the main line is now open again. Welcome back!